Lead-Time Guide

Avnet Abacus lead-time guide

 

All information is correct as of April 2024.

 

 

Connectors

      
Product Lead-time: weeks Lead-time: prognosis
Cable flat 13 =
Backplanes DIN 41612; 2MM; high speed; power signal; 14
I/O connectors 14 =
Memory card reader 14 =
Sockets DIP/SIP; PLCC/PGA/BGA; SIMM/IMM/Holtite 19 =
Non-solderable terminals/fastons 9 =
Circular military 21
Circular industrial 17 =
Circular medical 17 =
Rectangular military 21
Rectangular industrial 17 =
Rectangular medical 15 =
RF coaxial 15 =
Board to board 15 =
Wire to board/wire to wire 15 =
Automotive 19
Power - connector systems 19 =

 

Electromechanical

      
Product Lead-time: weeks Lead-time: prognosis
Switches 10 - allocation =
Relays general purpose 35 - allocation =
Relays automotive/telecom 35 - allocation =
Fans 19 - 52 =
Heatsinks 8 - 12 =
Sensors 10 - allocation =

 

Passive

      
Product Lead-time: weeks Lead-time: prognosis
Ceramic capacitors single layer 10 - 24 =
Ceramic capacitors leaded multilayer 20 - 30 =
Ceramic capacitors multilayer SMD  8 - 20+
Ceramic capacitors multilayer high CV 8 - 20+
Ceramic capacitors safety caps 16 - 30 =
Ceramic capacitors trimmer cap 16 - 30 =
Ceramic capacitors automotive 8 - 20+
Aluminium electrolytic capacitors leaded 8 - 26+
Aluminium electrolytic capacitors SMD 8 - 26+
Aluminium electrolytic capacitors snap-in & large can 8 - 26+
Film capacitors leaded 8 - 16+
Film capacitors SMD 8 - 16+
Film capacitors suppression 8 - 26+
Polymer capacitors 8 - 26+
Tantalum capacitors leaded 8 - 18
Tantalum capacitors SMD 8 - 18
Resistor SMD 16 - 20+ =
Resistor MELF/Metal film 14 - 20+ =
Resistor NLR 18 - 20
Resistor Potentiometer 16 - 20 =
Resistor Trimmer 14 - 16 =
Resistor Varistor 14 - 22
Resistor Wirewound 16 - 18 =
Resistor Networks/Arrays 18 - 20 =
Circuit protection - fuses 8 - 26+ =
Circuit protection - resettable devices 8 - 26+ =
Circuit protection - thermistors  8 - 26+  =
Circuit protection - varistors 8 - 26+ =
Antennas 12 - 30+ =
Frequency control crystals/oscillators 12 - 30+ =
Frequency control resonators 8 - 14 =
Electromagnetic piezo buzzers, sounders and transducers 8 - 14 =

 

Power

      
Product Lead-time: weeks Lead-time: prognosis
AC-DC PSU general purpose 20 - 48 =
AC-DC PSU medical 20 - 48 =
AC-DC PSU DIN rail 20 - 48 =
Rectifiers & front-end PSU 22 - 48 =
AC-DC external adaptors 20 - 48 =
AC-DC railway 20 - 48 =
AC-DC LED drivers general 20 - 48 =
AC-DC LED drivers special 20 - 48 =
DC-DC miniature 12 - 36 =
DC-DC industrial & bricks 12 - 48 =
DC-DC panel mount 12 - 48 =
DC-DC LED drivers 12 - 48 =

 

Filters and magnetics

      
Product Lead-time: weeks Lead-time: prognosis
Active filter 10 =
EMI filter 10 =
Power line filter 10 =
SAW filter 14 - 38 =
Ceramic filter 10 =
EMI/RFI filter 10 =
RF filter 10 =
Common mode chokes 10 - 30
Ferrite chip beads 10 - 12 =
Ferrite core 12 - 42 =
Inductor leaded 10 - 14+ =
Wireless charging coils 16 - 18 =
Inductor surface mount 8 - 80

 

Lead-time guide

Download a PDF version of the lead-time guide

Download

Ask an expert

Have a question? Our field applications engineers are on hand to help

Get in touch

Newsletters

Sign up to get the latest supplier lead-times straight to your inbox

Subscribe
 

 

Polymer vs MLCCs article Grid Box Dark

Display portlet menu

Technologies

Replacing MLCCs with polymer capacitors

Polymer capacitors are a viable alternative to MLCCs in a number of applications. Learn how some of their key characteristics compare and whether they could be suitable for your design.

An assortment of polymer capacitors

Technologies

Tackling recurring MLCC shortages

Fluctuating global MLCC demand is creating extremely challenging market conditions for the electronics industry. We can guide you through your options.

MLCCs on a PCB